Forgemasters help rebuild Russian disaster site

SHEFFIELD Forgemasters International is to supply major parts to a Russian hydro-electric power plant, which was wrecked by an explosion that killed 75 workers.

The Sayano-Shushenskaya station and dam, Russia's biggest hydro-electric power station, in south-central Siberia, can generate enough heat and light to a power a city of 3.8 million people.

However, the plant has not operated since an oil-filled transformer exploded last August.

Hide Ad
Hide Ad

Six of the 10 huge turbine units were damaged beyond repair and Sheffield Forgemasters International (SFIL) will be supplying hydro shafts for three of the replacement units as rebuilding work gets under way.

The shafts, each weighing more than 100 tonnes, connect the turbine runner to the generator. They are so large that SFIL is one of the few companies in the world capable of manufacturing them as a single forging.

The 1.6m order has to be completed by late summer and work has already started on the shafts, using the biggest forging ingot the company has available.

Volker Schaffer, sales director of Sheffield Forgemasters Engineering, said: "Rebuilding the plant is obviously going to be a massive job but it is such an important producer of energy, particularly as a supplier to the aluminium industry, that the Russian government is keen to have it operational again as quickly as possible.

Hide Ad
Hide Ad

"Obviously, this lends an element of urgency to the order and we have already started work on the shafts and fully expect to complete them in good time. We are hopeful that we may be asked to provide more shafts as and when work starts on rebuilding the remaining turbine units."

Most of the victims were working in the engine room, which houses the turbine units, when water flooded in after the explosion. The plant's dam was not damaged but the blast led to a three-mile oil slick spilling into the Yenisei river.

Russia's emergencies minister Sergei Shoigu has described the accident as "the biggest man-made emergency situation in the past 25 years for its scale of destruction, for the scale of losses it entails for our energy industry and our economy."