M1 traffic: Motorway to be closed and speed limits in place as major work carried out
Starting today (January 4), work will begin on the M1 Rainstorth Bridge between junction 34 (Meadowhall) and 35 (Thorpe Hesley), near Sheffield.
National Highways, the agency which looks after the country's major roads, will replace old steel grills and service ducts which give engineers access to the inside and underside of the bridge for safety inspections and servicing.
Advertisement
Hide AdAdvertisement
Hide AdThe work is expected to take around two to three months, and during this time there will be closures and speed limits enforced.
The M1 will be fully closed between junction 34 and 35 on one side of the carriageway and lanes 2, 3 and 4 closed on the opposite side. During full closures of either carriageway, lane 1 on the opposite side of the road will remain open to traffic. The northbound carriageway will be fully closed first. A 50mph speed limit will be in place for the safety of road users and the workforce.
Signed diversions will be in place, which have been agreed in advance with police and the local authority.
Southbound traffic will use the A629 and the A6109 before re-joining the M1 at Meadowhall Interchange. Northbound traffic will use the A6109 and A629 before re-joining the M1 at junction 35.
Advertisement
Hide AdAdvertisement
Hide AdNational Highways project manager Sujad Hussain said: “This work will make sure that the bridge remains in good condition, reducing the need for further repairs in the future.
"We will be working overnight both northbound and southbound, but not at the same time, and we will minimise disruption for road users attending events at Sheffield Arena by not starting work until later to allow them time to leave the venue.”